LESCO net metering update 2026

LESCO Net Metering Update 2026: New Billing Approval for Solar Connections Up to 25kW

Published: November 2, 2026  |  By: MFES Solar Energy

A new LESCO net metering update in October 2026 could help Lahore solar consumers whose older, eligible applications were approved but whose net-metering billing has not yet started. According to an October 29 news report, LESCO has delegated review and approval of certain pending billing cases for solar connections up to 25kW to the relevant circles.

The distinction matters: this is a step toward clearing eligible legacy billing cases, not an announcement that all new solar systems up to 25kW can enter the previous unit-for-unit net-metering scheme.

QUICK ANSWER  If your LESCO net-metering application was already in process before February 9, 2026 and you completed the required formalities by the applicable cut-off, your case may qualify for verification and billing approval. LESCO must confirm eligibility against official records.

What changed in the October 29 LESCO update?

Pakistan Point reported on October 29, 2026 that the authority to review eligible net-metering billing cases for solar connections of up to 25kW had been delegated to the relevant LESCO circles. Under the reported arrangements, the Deputy Director (Technical) can scrutinize qualifying files and approve billing according to the prescribed policy.

Previously, some customers reportedly had installed solar equipment or completed parts of the approval process but continued to receive conventional electricity bills while their net-metering status remained unresolved. Moving the review closer to the relevant circle may help address this administrative backlog. However, no universal processing deadline was announced in the report.

Source: Pakistan Point report, October 29, 2026

Who may qualify for the pending net-metering billing approval?

The August 25 Power Division instructions focused on legacy applications involving required actions before February 9, 2026. They emphasized verifiable payment of the demand notice before that date and checks of the relevant approvals, meter work and connection records. The October 29 report also referred to timely agreements and demand notices.

For a Lahore homeowner or business owner, the strongest supporting records may include:

  • Original net-metering application and acknowledgment or reference number.
  • Paid demand notice with evidence of payment made before February 9, 2026.
  • Signed interconnection agreement and available approval/concurrence documents.
  • Meter replacement or reprogramming records, where applicable.
  • Recent LESCO bill and any earlier written correspondence about pending billing.

These are useful records to assemble for review, not a promise that each file meets every legal condition. LESCO and the applicable regulatory directions determine eligibility in individual cases.

Why is February 9, 2026 so important?

NEPRA’s Prosumer Regulations 2026 took effect on February 9, introducing a net-billing framework for new grid-connected solar arrangements. Existing qualifying agreements under the earlier regulations received separate protection through a later amendment. During the changeover, some applications remained pending despite consumers having completed major steps before the cut-off.

The Power Division therefore directed distribution companies and the Pakistan Information Technology Company (PITC) in August to verify legitimate pending cases and align billing records. For practical date checking, “before February 9” generally means the relevant action had occurred no later than February 8, 2026, but a customer should have LESCO verify the precise dates and requirements for their application.

How many pending applications have been cleared?

The September 5, 2026 federal update reported 16,654 applications pending nationwide during the policy transition. Of those, 11,695 had been cleared or verified at that point, while verification of 4,959 others was continuing. Those figures are nationwide, not a separate count for LESCO, and should not be treated as the latest live status of an individual case.

The October LESCO development is relevant because even where application verification has progressed, customers still need the correct billing setup and confirmation from the responsible utility office.

How to check a pending LESCO net-metering case

  1. Gather your records. Keep your consumer/reference number, dated application, paid demand notice, agreement and meter-related documents together.
  2. Check the government verification channel. The Power Division identified nmverification.pitc.com.pk for status checks of pending transition-era cases. Access may vary; if unavailable, continue directly with LESCO.
  3. Contact the relevant LESCO circle. Ask whether your case is in the eligible legacy-billing review process and whether it has reached the Deputy Director (Technical).
  4. Request a written billing-status update. If your system is installed but the bill still does not reflect the approved arrangement, ask when the correction will be applied and whether a billing adjustment is due under the applicable rules.
  5. Avoid unauthorized processing payments. The Power Division says eligible consumers should not pay an individual or middleman to expedite this verification process.

Official verification route: PITC net-metering verification portal (cited by the Power Division, September 5, 2026).

Does this mean new 25kW solar customers can get old net metering?

No. Two separate 2026 developments are easy to confuse:

  • August 6 NEPRA amendment: For a new distributed-generation facility of 25kW or less, the relevant distribution company can grant the required approval without a separate NEPRA concurrence. This is an administrative approval change within the 2026 prosumer framework.
  • October 29 LESCO report: Eligible older connections of up to 25kW with unresolved net-metering billing may be reviewed and approved at circle level, subject to the legacy-case criteria.

So, a homeowner planning a fresh solar installation in Lahore should not assume that the October news restores the former one-for-one export adjustment. For the current approach to electricity imports, exports and self-consumption, see MFES’s Net Billing Pakistan 2026 Guide.

What does this mean for Lahore solar consumers?

For customers with genuine older pending cases, the update may offer a more direct administrative route to review and correct their billing category. The financial outcome still depends on their actual agreement, meter status, verified application dates, electricity consumption and final LESCO decision.

For new solar customers, the main priorities remain correct system sizing, qualified electrical installation, regulatory compliance and realistic savings estimates. Solar reduces reliance on purchased electricity, but fixed charges and applicable bill components may still remain. Explore MFES’s residential solar solutions in Lahore for planning guidance.

Frequently asked questions

1. Has LESCO reopened old net metering for all new solar users?

No. The October 29 report concerns eligible pre-existing cases awaiting billing approval; it does not give all new installations the old net-metering terms.

2. Are all solar systems up to 25kW automatically eligible?

No. The 25kW threshold describes the size category covered by the reported circle-level review, not automatic eligibility. The application history and required documents still matter.

3. What if my demand notice was paid after February 8, 2026?

The August 25 government instructions identify verifiable payment before February 9 as a key condition for the legacy verification exercise. Ask LESCO to review your exact records rather than assuming you qualify.

4. Where can I check my pending application status?

The Power Division named nmverification.pitc.com.pk for transition-era pending cases. You can also contact the relevant LESCO circle with your application and consumer-reference details.

5. How long will LESCO take to approve the billing?

The October 29 report did not specify a guaranteed completion period. The timeline depends on document verification, the relevant LESCO office and billing-system updates.

Conclusion: A useful update for eligible LESCO solar owners

The latest LESCO net metering update is a positive administrative development for Lahore consumers with eligible, pending legacy billing cases of up to 25kW. It may make it easier to have a case reviewed by the relevant circle—but it is not a universal return to the old net-metering policy.

If you are planning a new solar installation in Lahore or need guidance understanding the technical status of an existing installation, MFES Solar Energy can help you assess your system and documentation. Final approval and billing decisions remain with LESCO and the responsible authorities.

Speak to MFES Solar Energy: 0300-1599957  |  Request a consultation 

 

Source references & editorial notes

Use these verified links for factual support and outgoing references. The October 29 article is a news report attributed to sources; a publicly accessible LESCO circular confirming each procedural detail was not located during this research. Do not present the reported delegation as an independently verified LESCO notification.